This project that we worked on was a power swap project on Ufone base transceiver sites. It consisted of power swap on 135 Ufone sites in the northern region and 96 Ufone sites for the centre region of Pakistan.
The project installation and ATP phase of the 231 sites spanned two months i.e. from 18th January till 18th  March 2016.

 

 